Site Visit Program for 440 MW in UP Solar Park under JNNSM Ph-II, Batch-III

Start Date:- 12-17-15 End Date:- 12-24-15

This has reference to the RfS documents issued by SECI for setting up of 440 MW grid connected solar PV projects in the state of UP vide RfS No. SECI/JNNSM/P-2/B-3/RfS/UP/092015 dated 24.09.2015 under JNNSM Ph-II Batch –III Tranche-III.

The program schedule for the site visit and the respective Project Officer (UPNEDA) contact details are as mentioned below:

Sl. No. Location (District) Site Visit date Project Officer Contact Number
1 Allahabad 19/12/2015 Shri Rajmani Pandey 09415609026
2 Kanpur Dehat 21/12/2015 Shri RadheyShayam 09415609053
3 Jalaun 22/12/2015 Shri Shivdarshan/ Shri D.P.Singh 09415609050/09451595774
4 Mirzapur 23/12/2015 Shri Sanjay 09415609065

 

The prospective bidders are requested to contact the respective project officer in advance and make necessary arrangements on their own for the site visit.